Bi-Courtney deserves kudos on Lagos-Ibadan Expressway

NEARLY six months after the Federal Government (FG) revoked the Lagos-Ibadan Expressway concession given to Bi-Courtney Limited (BCL), Nigerians can now see that the firm deserves praises for saving the highway from total collapse while various interest groups were working against the success of the project.

While announcing the termination of the concession agreement on November 19, 2012, at an emergency press conference addressed by the Minister of Works, Arch. Mike Onolememen, the FG stated that two construction firms would fix the road before Christmas but not much has been done. Things are now getting so bad on the road.
Bi-Courtney left the road in a much better condition than it was in 2009, when it won the concession for its reconstruction under a Design, Build, Operate and Transfer (DBOT) agreement with FG.
The situation must be reassessed because the problem was in the system not the concessionaire. At some points, the firm's efforts were commended by road users, the Minister of Works and top officials of the Ministry who were supervising the project.
To fault the claims by the Federal Ministry of Works that Bi-Courtney did not carry out any palliative works on the road before the controversial termination of the concession agreement, read an interview, which Arch. Onolememen granted Saturday Punch, on September 17, 2011, in which he was quoted as follows:

“I saw the concessionaire handling the road and he briefed me about some problems on the road, which according to him are being resolved now. But I had to also instruct him that in 60 days, I wanted all potholes on that road fixed so that road users can use the road without hardship and I am happy to say that to a very large extent, the concessionaire has complied. I am saying this because a few days ago, the Vice Chancellor of the University of Agriculture, Abeokuta, called me while driving through that road in the night, about 8pm and said ‘congratulations your ultimatum is working. For the first time I am seeing a Nigerian contractor working with floodlight in the night, patching potholes and all that’. I think that is a very good development.”

Under the concession agreement, BCL was expected to raise N89.5 billion needed to transform the dual carriageway into an ultra-modern super-highway that would be comparable to any other in the world.
But a Federal Government appointed umpire, the Infrastructure Concession Regulatory Commission (ICRC) explained in its report submitted to the President that the project failed because the government did not play its part well as a partner in the Public Private Partnership (PPP) enterprise.
In its 2011 annual report delivered to President Goodluck Jonathan by the Chairman, Chief Ernest Shonekan, ICRC noted that the implementation of the project was delayed due to various issues that were not addressed prior to the execution of the contract.

“It is evident that the scope of the work was not fully documented and outline design provided before the concession was awarded,” says the report.

ICRC identified some of the issues as approval for the design of the road, securing the Right of Way, Financial Model and Environmental and Social Impact Assessment.

The report says that approval for a final design was granted on May 10, 2011, two years after the concession agreement was signed.

On the financial model, the commission observed that the cost of the project as included in the concession agreement was not based on the necessary studies.

The report reads in part: “Without an agreed design and scope of works based on the grantor’s performance and output standards, there cannot be an agreed fixed cost for the project.

“Without a financial model setting out the expected project costs and revenues, financing costs cannot be determined.

“The cost of the project as included in the concession agreement was not based on the necessary studies (e.g. traffic forecast) required for the implementation of a road project through DBOT model.”

According to ICRC an environmental and social impact assessment should have been carried out because of the extent of the refurbishment work, the proposed widening and the effect that tolling was likely to have on the properties and communities along the road.

The report also states that further traffic data and survey work ought to have taken place to assess the willingness and ability of the road users to pay, and potential diversionary effects, adding that extended right of ways ought to have been secured.

“Due to the issues identified above, the project could not raise finance from any credible investor. This made it impossible for the concessionaire to meet the conditions precedent as itemised in Article3.3 of the concession agreement,” the report says.
Bi-Courtney should also be absolved of blame for the spate of automobile accidents on the road, a significant number of which resulted in the loss of lives, noting that official statistics by the Federal Road Safety Corps actually showed that the rate of accidents on the road reduced, after the firm took over its maintenance from the works ministry.

The company recalled the deplorable condition of some sections of the Ibadan end of the road, especially around ARAMED Hospital, before it was “reconstructed by BCL, at a very huge cost in both material and expertise, a fact that can be attested to by regular users of that section of the road”.

BCL further called the attention of Nigerians to a media statement credited to the Director in-charge of PPP in the works ministry, Engr. Tunde Ekunsumi, after an assessment of the progress and quality of work by Borini Prono, the company hired by BCL to commence major reconstruction of the expressway few days before the federal government purportedly terminated the agreement.

Ekunsumi, according to BCL, was quoted by the News Agency of Nigeria (NAN) and some newspapers as follows: “The Ministry was satisfied with the progress of work done by the contractors, Messrs Borini Prono. The contractor was working in line with general certification of both the ministry and international standard. I think they have done very good, bearing in mind the intervention of weather.”

The company equally observed that “the expressway would have become totally impassable if, indeed, we have failed to maintain it since 2009. It was for this purpose that we procured a $6.5 million asphalt plant, which was confiscated by the Ogun State government and had not been released till date.

After the visitation of the Minister to the Lagos-Ibadan Expressway on July 23, 2011, fresh palliative works were done. It was the fourth time such extensive work was done by BCL on the road, since the concession was granted in 2009.

Bi-Courtney worked over long stretches of the road at Ibafo, along the southbound carriageway, where the whole length was cleared and backfilled. This work contributed appreciably to ease traffic congestion normally experienced along the stretch.

The firm overlaid long stretches at Fidiwo, Sapade, Alapako, and Kilometre 90, near Ibadan; Fatgbems, at Isheri; Ibafo, and RCCG area, northbound from Danco Filling Station towards Conoil Filling Station.

These clarifications became necessary following the series of misinformation and misconception being promoted among the public by persons with personal interest in the expressway, other than the overall interest of the citizenry and the nation at large.

 

 