Bi-Courtney deserves kudos on Lagos-Ibadan
Expressway
NEARLY six months after the Federal
Government (FG) revoked the Lagos-Ibadan Expressway concession given to
Bi-Courtney Limited (BCL), Nigerians can now see that the firm deserves praises
for saving the highway from total collapse while various interest groups were
working against the success of the project.
While announcing the termination of the
concession agreement on November 19, 2012, at an emergency press conference
addressed by the Minister of Works, Arch. Mike Onolememen, the FG stated that
two construction firms would fix the road before Christmas but not much has
been done. Things are now getting so bad on the road.
Bi-Courtney left the road in a much better condition than it was in 2009, when it
won the concession for its reconstruction under a Design, Build, Operate and
Transfer (DBOT) agreement with FG.The situation must be reassessed because the problem was in the system not the concessionaire. At some points, the firm's efforts were commended by road users, the Minister of Works and top officials of the Ministry who were supervising the project.
To fault the claims by the Federal
Ministry of Works that Bi-Courtney did not carry out any palliative works on the road before
the controversial termination of the concession agreement, read an
interview, which Arch. Onolememen granted Saturday Punch, on September 17,
2011, in which he was quoted as follows:
“I saw the concessionaire handling the road
and he briefed me about some problems on the road, which according to him are
being resolved now. But I had to also instruct him that in 60 days, I wanted
all potholes on that road fixed so that road users can use the road without
hardship and I am happy to say that to a very large extent, the concessionaire
has complied. I am saying this because a few days ago, the Vice Chancellor of
the University of Agriculture, Abeokuta, called me while driving through that
road in the night, about 8pm and said ‘congratulations your ultimatum is
working. For the first time I am seeing a Nigerian contractor working with
floodlight in the night, patching potholes and all that’. I think that is a
very good development.”
Under the concession agreement, BCL was
expected to raise N89.5 billion needed to transform the dual carriageway into
an ultra-modern super-highway that would be comparable to any other in the
world.
But a Federal Government appointed umpire,
the Infrastructure Concession Regulatory Commission (ICRC) explained in its
report submitted to the President that the project failed because the
government did not play its part well as a partner in the Public Private
Partnership (PPP) enterprise.
In its 2011 annual report delivered to
President Goodluck Jonathan by the Chairman, Chief Ernest Shonekan, ICRC noted
that the implementation of the project was delayed due to various issues that
were not addressed prior to the execution of the contract.
“It is evident that the scope of the work
was not fully documented and outline design provided before the concession was
awarded,” says the report.
ICRC identified some of the issues as
approval for the design of the road, securing the Right of Way, Financial Model
and Environmental and Social Impact Assessment.
The report says that approval for a final
design was granted on May 10, 2011, two years after the concession agreement
was signed.
On the financial model, the commission
observed that the cost of the project as included in the concession agreement
was not based on the necessary studies.
The report reads in part: “Without an
agreed design and scope of works based on the grantor’s performance and output
standards, there cannot be an agreed fixed cost for the project.
“Without a financial model setting out the
expected project costs and revenues, financing costs cannot be determined.
“The cost of the project as included in the
concession agreement was not based on the necessary studies (e.g. traffic
forecast) required for the implementation of a road project through DBOT
model.”
According to ICRC an environmental and
social impact assessment should have been carried out because of the extent of
the refurbishment work, the proposed widening and the effect that tolling was
likely to have on the properties and communities along the road.
The report also states that further traffic
data and survey work ought to have taken place to assess the willingness and
ability of the road users to pay, and potential diversionary effects, adding
that extended right of ways ought to have been secured.
“Due to the issues identified above, the
project could not raise finance from any credible investor. This made it
impossible for the concessionaire to meet the conditions precedent as itemised
in Article3.3 of the concession agreement,” the report says.
Bi-Courtney should also be absolved of blame for the
spate of automobile accidents on the road, a significant number of which
resulted in the loss of lives, noting that official statistics by the Federal
Road Safety Corps actually showed that the rate of accidents on the road
reduced, after the firm took over its maintenance from the works ministry.
The company recalled the deplorable
condition of some sections of the Ibadan end of the road, especially around
ARAMED Hospital, before it was “reconstructed by BCL, at a very huge cost in
both material and expertise, a fact that can be attested to by regular users of
that section of the road”.
BCL further called the attention of
Nigerians to a media statement credited to the Director in-charge of PPP in the
works ministry, Engr. Tunde Ekunsumi, after an assessment of the progress and
quality of work by Borini Prono, the company hired by BCL to commence major
reconstruction of the expressway few days before the federal government
purportedly terminated the agreement.
Ekunsumi, according to BCL, was quoted by
the News Agency of Nigeria (NAN) and some newspapers as follows: “The Ministry
was satisfied with the progress of work done by the contractors, Messrs Borini
Prono. The contractor was working in line with general certification of both
the ministry and international standard. I think they have done very good,
bearing in mind the intervention of weather.”
The company equally observed that “the
expressway would have become totally impassable if, indeed, we have failed to
maintain it since 2009. It was for this purpose that we procured a $6.5 million
asphalt plant, which was confiscated by the Ogun State government and had not
been released till date.
After the visitation of the Minister to the
Lagos-Ibadan Expressway on July 23, 2011, fresh palliative works were done. It
was the fourth time such extensive work was done by BCL on the road, since the
concession was granted in 2009.
Bi-Courtney worked over long stretches of the road
at Ibafo, along the southbound carriageway, where the whole length was cleared
and backfilled. This work contributed appreciably to ease traffic congestion
normally experienced along the stretch.
The firm overlaid long stretches at Fidiwo,
Sapade, Alapako, and Kilometre 90, near Ibadan; Fatgbems, at Isheri; Ibafo, and
RCCG area, northbound from Danco Filling Station towards Conoil Filling
Station.
These clarifications became necessary
following the series of misinformation and misconception being promoted among
the public by persons with personal interest in the expressway, other than the
overall interest of the citizenry and the nation at large.